I posted this in RTK - Rick Parry but thought it was suited in here. The below is from another forum this guy soke with Parry while at the RTK meeting. Looks like to start with will be 66k - hopefully !
I attended the RTK Q&A session tonight with the aim of asking about the new stadium, but understandably the evening was dominated by events in Athens, the clubs response, the Final ticket issue & genrally loyalty.
Hence, I didn't get to ask my question. I did manage to speak with Rick Parry at the end and he confirmed the following;
The Revised design requires a fresh planning application, to by pass the majority of the delays and objections, the capacity will remain the same, ie 61k, however Parry said the KOP was stunning and it will be around 19k in capacity. The reason why the 61k is the same, is because all the transport infrastructure issues & objections have been looked at & from what I can gather this will allow us to get approval to start building ASAP.
Not wanting to give ammunition to people who object to the ground, Parry went onto say the club may or may not (IMO we will) then put in another application to upgrade the capacity to 66k, while the work is in progress, with a view to completing the stadium on time with 66k capacity, in the same amount of time that they would have completed it with 61k.
I then asked about a upper limit & it appears that the figure mooted was 76k, but this would be dependant on a number of things, including the reopening of the Bootle Branch line & the reserection of the tram scheme, but who knows, maybe with the Yanks help?
Other notable figures from the evening;
Currently 60k on the season ticket waiting list & currently 166k fan card holders.